LLRain-0936

Cedar Brake Concrete

Today crews poured the foundation for what will become the Main Cabin at Cedar Brake. This building acts as a sort of hub for the site and will include a kitchen, dining and meeting spaces, generous porches and two residency units.

Details

Site Visit: February 9, 2017

Laity Lodge was swarming with activity this morning. Painters, landscapers, carpenters, drywall hangers, tile and door installers, electricians, irrigators, masons, plumbers, ac/heating rough-in crew, concrete polishers, and a foundation crew were all busy both with their tasks and with keeping out of each other’s way. But with clear skies and 70 degrees in early February, nobody was complaining.

Details

Summer Schedule Changes

Last week, only hours before we published the summer retreat schedule, our on-site construction manager let us know that it was suddenly doubtful the work would be finished by June. After a week of further review and consultation, we’ve made the painful decision to cancel our summer retreats and push the Laity Lodge reopening to September 2017.

Details